Number sequence gap issues for Orders in Ax 2012

Some time we noticed that there is Number sequence gap issues for Orders in Ax 2012 like you have created SO00001 then after sometimes you created then you got order SO00004 is creating instead of SO00002.

Reason for this kind of issue is as follow.

1.If you check to number sequence type then you will find that a continuous number sequence could be setup as Order.

2. If you create a new order and then delete it, no numbers added to the status list which can be freed and used again system maintain itself.

3. If you create a new order using but then you cancel it for example "Create sales order" form, and click "cancel" in the form then the number will be added to the status list. Then the number can be freed by clean-up and can be used again when a new order is created.

I hope you can get Idea from above observation.

Popular posts from this blog

How to set up parent project in project accounting in ax 2012

create simple project and then go to the project hierarchy fast tab and there you must define sub-project ID format "-#" and then your sub-project will be enabled. For resource assigning in Project first you need to configure the HR module, in that you need to maintain the calendar for those employees and then you need to define the cost of that particular employee (for expense) and for Revenue you need to define the sales price of that particular employee. In the project accounting module you need to mention the calendar in scheduling fast tab and then you need to define WBS, in WBS activity you can be able to assign resources.

ERD Account Payable and Account Receivable in ax 2012